Installation Process of Jumbo Bag Filling Machine (Step-by-Step Guide)

Installation Process of Jumbo Bag Filling Machine (Step-by-Step Guide)

Installing a Jumbo Bag Filling Machine is not very hard if you follow the correct steps. But it must be done carefully. A small mistake can create big problems later.

This guide explains the complete installation process of jumbo bag filling machine in very simple words. Even if you are new to this machine, you will understand everything clearly.

We will cover

-> Site preparation
-> Machine unloading
-> Mechanical setup
-> Electrical connection
-> Air connection
-> Trial run
-> Safety checks
-> Final testing

Let’s start from the beginning.

What Is a Jumbo Bag Filling Machine?

A Jumbo Bag Filling Machine is used to fill large bags (also called FIBC bags, bulk bags, or super sacks) with powder, granules, or bulk material.

These bags are usually 500 kg to 2000 kg capacity.

This machine is also known as:

-> Big Bag Filling Machine
-> Bulk Bag Filling System
-> Super Sack Filling Machine
-> FIBC Filling Machine

Before using the machine, proper installation is very important.

Why Proper Installation Is Important?

Correct installation helps in:

-> Accurate weight filling
-> Smooth machine working
-> Long machine life
-> Worker safety
-> Less maintenance problem

If installation is wrong:

-> Machine vibration increases
-> Weight accuracy becomes poor
-> Parts get damaged fast
-> Production stops frequently

So, always follow the proper jumbo bag filling machine setup procedure.

Step 1: Site Preparation Before Installation

Before bringing the machine, prepare the site properly.

1. Strong Floor Foundation

The machine is heavy. The floor must be:

-> Strong concrete base
-> Flat and level
-> Vibration-free

If the floor is weak, machine alignment will disturb.

2. Enough Space

Keep enough space around the machine for:

-> Operator movement
-> Forklift movement
-> Bag loading and unloading
-> Maintenance work

Minimum 1–1.5 meter space around machine is recommended.

3. Power Supply Ready

Check:

-> Voltage requirement
-> 3-phase connection (if required)
-> Proper earthing

4. Air Supply Arrangement

Most bulk bag filling systems need compressed air.

Install:

-> Air compressor
-> Air dryer (if required)
-> Air pipeline near machine

Step 2: Machine Unloading and Positioning

After the machine reaches your factory:

1. Safe Unloading

Use:

-> Crane
-> Forklift
-> Lifting belts

Do not lift from weak points. Always lift from recommended lifting hooks.

2. Check for Damage

Before installation:

-> Inspect for transport damage
-> Check panels, load cells, frame
-> Verify all parts received

3. Position the Machine

Place the machine at the exact installation point.

Make sure:

-> It is aligned properly
-> It is centered with material feeding system

This is part of the big bag filling machine installation process.

Step 3: Mechanical Installation

Now we begin the actual jumbo bag filling machine setup.

1. Fix the Machine to Floor

Use:

-> Anchor bolts
-> Proper drilling
-> Tight fitting

This prevents vibration during operation.

2. Level the Machine

Use spirit level to check:

-> Front side
-> Back side
-> Left and right

Machine must be perfectly level. Otherwise weight accuracy will change.

3. Install Feeding System

Connect:

-> Screw feeder
-> Belt conveyor
-> Gravity feeding hopper

Make sure material flows smoothly.

4. Attach Bag Holding System

Fix:

-> Bag hanging hooks
-> Inflatable neck clamps
-> Bag support platform

These parts hold the FIBC bag properly during filling.

Step 4: Electrical Installation

This step must be done by a qualified electrician.

1. Main Power Connection

Connect main power cable to:

-> Control panel
-> Motor
-> Load cells

Check voltage before switching ON.

2. Proper Earthing

Earthing is very important for:

-> Safety
-> Protection from electric shock
-> Stable weight reading

3. Control Panel Check

Verify:

-> Display working
-> Buttons responding
-> Emergency stop functioning

This completes the electrical part of the FIBC filling machine installation steps.

Step 5: Pneumatic (Air) Connection

Most super sack filling machines use air for:

-> Bag clamping
-> Dust control
-> Gate opening & closing

1. Connect Air Line

Connect air pipe to:

-> FRL unit (Filter, Regulator, Lubricator)
-> Pneumatic valves

2. Set Air Pressure

Normal air pressure: 5–7 bar (depends on machine model)

-> Too high pressure can damage cylinders.
-> Too low pressure will not clamp bag properly.

Step 6: Load Cell Calibration

Load cells are used for weight measurement.

This is a very important part of the installation process of jumbo bag filling machine.

1. Zero Calibration

Turn ON machine and:

-> Remove all weight
-> Set zero value

2. Test Weight Calibration

Place known weight (example: 50 kg)

Check:

-> Display shows correct weight
-> Adjust if needed

Correct calibration ensures accurate filling.

Step 7: Trial Run Without Material

Before real production:

Do a dry run.

Check:

-> Motor rotation direction
-> Air cylinder movement
-> Gate opening & closing
-> Control panel settings

Fix problems if found.

Step 8: Trial Run With Material

Now test with small quantity material.

1. Hang Empty Bag

Attach FIBC bag properly.

2. Start Filling

Observe:

-> Material flow
-> Dust control system
-> Weight accuracy

3. Check Final Weight

If target is 1000 kg:

-> Check final weight on weighing scale
-> Adjust fine feeding speed if needed

This step is called commissioning process of bulk bag filling machine.

Step 9: Safety Checks

Safety is very important.

Check:

-> Emergency stop button
-> Overload protection
-> Safety guards
-> Proper grounding

Train operators before starting full production.

Step 10: Final Inspection and Handover

After successful trial:

-> Tighten all bolts
-> Clean machine
-> Prepare installation report
-> Provide operator training

Now machine is ready for regular production.

Common Problems During Installation

Here are some common mistakes:

1. Uneven Floor

Result: Wrong weight reading.

2. Loose Bolts

Result: Vibration and damage.

3. Wrong Air Pressure

Result: Bag clamp failure.

4. Improper Calibration

Result: Underfilling or overfilling.

Avoid these mistakes during industrial bag filling machine installation.

Tools Required for Installation

Basic tools needed:

-> Spanner set
-> Drill machine
-> Spirit level
-> Multimeter
-> Air pressure gauge
-> Test weights

Having proper tools makes the machine setup procedure easy.

How Long Does Installation Take?

Normally:

-> Small machine: 1–2 days
-> Medium system: 2–3 days
-> Fully automatic system: 3–5 days

Time depends on:

-> Site readiness
-> Machine size
-> Number of connected systems

Who Should Install the Machine?

Installation should be done by:

  • Manufacturer technician
    OR
    Experienced mechanical and electrical team

Professional installation ensures:

  • Proper performance

  • Warranty protection

  • Long life

Maintenance Tips After Installation

After successful jumbo bag filling machine setup, follow these tips:

-> Check bolts weekly
-> Clean load cells
-> Maintain air pressure
-> Lubricate moving parts
-> Calibrate weight monthly

Regular maintenance avoids production problems.

Important Safety Tips

Always remember:

-> Never stand under hanging bag
-> Use safety gloves
-> Do not open panel when power ON
-> Keep area clean
-> Train all operators

Safety first, always.

Final Words

The Installation Process of Jumbo Bag Filling Machine is not complicated, but it must be done carefully and step by step.

If installation is done correctly:


-> Machine runs smoothly
-> Weight accuracy stays perfect
-> Production increases
-> Maintenance cost reduces

Whether you call it:

->Jumbo Bag Filling Machine Installation
-> Big Bag Filling Machine Setup
-> FIBC Filling Machine Installation Guide
-> Bulk Bag Filling System Setup
-> Super Sack Filling Machine Commissioning

The process remains mostly the same.

Always follow proper steps, use trained technicians, and test the machine properly before starting full production.

A well-installed machine works better, lasts longer, and gives you peace of mind.

Scroll to Top
Call Now Button